A new molded fiber project often arrives in our inbox as a very short request:
“We need a 5-ton-per-day production line. Please quote.”
The number is useful, but it is not enough to design a factory.
Five tons of what?
How many products?
What is the average unit weight?
What raw material will be used?
How many hours will the plant operate each day?
These questions will be part of our discussions at the 140th Canton Fair in Guangzhou, October 23–27, 2026.

Question 1: What Will the Factory Actually Produce?
The product determines much of the engineering.
A factory focused on plates has a different mold strategy from one producing deep containers, bowls and lids.
A plant running two stable SKUs is easier to schedule than one expected to switch between twenty products.
This is why product planning should come before machine quantity.

Question 2: Do You Need Tons Per Day or Pieces Per Day?
Investors usually talk in tons.
Sales departments usually talk in pieces.
Both are necessary.
A production line designed only around total tonnage may look sufficient on paper but still fail to produce enough pieces of a lightweight SKU.
For a practical plant design, the calculation should move from monthly sales demand to daily piece demand, product weight, mold cavities, cycle time and finally the number of machines required.

Question 3: Can the Utilities Support the Machines?
A forming machine does not operate in isolation.
The factory also needs pulp preparation, vacuum, compressed air, water circulation, heating and electrical capacity.
If one supporting system is undersized, the forming section cannot run at its intended rate.
This is one of the reasons turnkey planning matters.
A good factory layout is not simply a drawing of where machines fit.
It is a plan for how material, energy, products and people move through the building.

Question 4: How Much Automation Is Worth Paying For?
More automation is not automatically better.
The correct level depends on labor cost, order stability, product type and plant scale.
For a large factory running standard products around the clock, automatic transfer and stacking can produce meaningful labor savings.
For a smaller project, investment priorities may be different.
The right question is not “How automated can the factory be?”
It is “Where does automation remove the most repetitive cost and risk?”

Question 5: What Happens When Demand Doubles?
A factory should not be designed only for the first order.
Future expansion deserves space in the original plan.
That may mean leaving room for additional forming machines, reserving utility capacity or designing a pulp system that can support future modules.
Planning expansion early is almost always easier than redesigning a crowded production floor later.

Talk About the Whole Project in Guangzhou
At Canton Fair 2026, Far East will discuss more than individual machines.
Customers planning new plants or factory expansions can bring:
a product list, factory drawing, target capacity or even an early investment concept.
From there, we can discuss equipment quantity, molds, utilities, layout and the sequence required to move from concept to production.